Custom card MOQ is 500 decks for standard specifications, because plate making, die cutting and machine setup cost the same whether you print 200 or 20,000. Sampling runs 5–7 working days and mass production 15–20 days after proof approval, with foil and rigid boxes adding the most time.
Where the 500 comes from
A deck order carries fixed costs before a single sheet is printed: four plates per side, a die for the card shape, a die for the box, machine setup and a proof. Those costs do not shrink with quantity. At 500 decks they are spread thinly enough to be invisible; at 100 decks they dominate the price.
This is why a 100-deck order can cost 60–80% of a 500-deck order. The supplier is not penalising you; the setup is the same.
| Order size | Per-deck cost | Practical notes |
|---|---|---|
| 1–50 | Sample scale | Digital or hand-finished; not for retail |
| 200–300 | +20–40% | Viable first run for oracle or promo decks |
| 500 | Baseline | Standard MOQ; full offset quality |
| 1,000–5,000 | −10–25% | Packing becomes the constraint, not printing |
| 10,000+ | −25–35% | Needs a confirmed schedule slot |
Sampling: five to seven days, and worth all of them
A sample is not a courtesy; it is the risk control for the whole order. We print the sample on the final stock with the final lamination, because a digital proof on office paper cannot show you snap, edge colour or how a dark back reads through a pale face.
Three things speed sampling up: files that pass preflight on the first pass, a decision on foil and varnish before the sample is scheduled, and a single approver on your side. Three things slow it down: artwork revised after plates, a box that changes after the deck is approved, and feedback split between several stakeholders.
The production calendar, milestone by milestone
- Day 0: proof and specification signed; deposit received.
- Day 1–2: preflight and plate making.
- Day 2–6: printing, then lamination and curing.
- Day 6–9: die-cutting, sorting and any foil or edge work.
- Day 9–14: box making, collation and packing.
- Day 14–20: QC inspection, carton labelling and handover.
The calendar assumes a plain deck. Add 2–4 days for gilded edges, 2–4 days for foil, and 5–7 days if a rigid box or a guidebook is produced in the same order.
What actually delays a run
- Artwork changes after plates. This restarts the clock, not pauses it.
- Late approval on a box die, which is the longest-lead item in the project.
- Chinese New Year and the two weeks around it, when most factories slow down.
- Colour approval by committee, especially across time zones.
- Payment arriving after the production slot was reserved for someone else.
Can production be expedited?
Sometimes, and honestly it depends on the line at that moment. A plain deck can occasionally be pulled forward by 3–5 days. A gilded or foil deck usually cannot, because the extra passes need curing time that cannot be compressed without risking scuffing. Ask early, and treat any promise as conditional until the deposit and files are in.
How custom card MOQ affects packaging
The card MOQ is only half of the order. Packaging has its own minimums, and they are usually higher than the deck's. A box printer may need 1,000 units to justify a die and a print setup, and a tin may need 2,000. This is why a 500-deck order often ships in a stock box with a printed label.
Three options exist at small quantities, and each has a trade-off. A stock box with a printed label is cheapest and looks generic. A stock box with a printed sleeve reads as custom and needs no die. A custom die-cut box is the best result and the worst first-run economics, because the die is a fixed cost that only amortises over larger quantity.
The arithmetic is simple: divide the die and setup cost by the order quantity and compare that number with the difference in perceived value. At 500 units, a custom rigid box can add 30–40% to the unit cost. At 5,000 it adds 4–6%.
- Ask for the box price at 500, 1,000 and 5,000 before choosing the format.
- Confirm whether the box die can be reused for a reprint, and for how long.
- Check the carton count: a rigid box does not pack flat, so freight per unit rises.
- Keep a stock-box fallback for the first run if the launch date is fixed.
Our card boxes and booklets page covers the formats we tool in-house, and project and sample types explains how a prototype order is priced against a production order. If the packaging uses certified board, confirm the printer against the FSC register.
A 30-day first order, planned backwards
Most first-time buyers work forwards from the artwork and run late. Work backwards from the launch date instead, and the critical path becomes obvious: the box die, not the cards, is usually the item that decides whether you ship on time.
A realistic 30-day calendar: days 1–3 quotation and specification; days 4–7 artwork preflight; days 8–14 sample; days 15–16 approval and deposit; days 16–24 print, laminate, die-cut; days 24–28 pack and inspect; days 28–30 handover to courier. A rigid box adds five days at the front because the die has to be made before the sample can be built.
Two slack points are worth protecting. Keep three days between sample approval and the print date, because colour comments often arrive in two rounds. Keep two days between packing and handover, because the carton labels are where a marketplace specification usually gets missed.
Payment, deposits and what they secure
A deposit does two things: it books a production slot and it authorises the fixed costs, which is why it is usually non-refundable once plates are made. Ask what the deposit covers and when the balance is due. A supplier who asks for the full amount before printing is removing your leverage; one who asks for nothing before plates is carrying all the risk and will price it in.
For a first order, the usual structure is 30–50% with the purchase order and the balance before shipment, after inspection photos. Agree the inspection point in writing: a buyer who inspects before the cartons are sealed can still fix a problem; a buyer who inspects at the destination is filing a claim.
How to hit a small MOQ without a bad sample
A custom card MOQ of 500 is not a wall; it is the point where fixed costs stop dominating the unit price. The mistake at small quantity is to save on the sample. A 200-set run in a stock box is a legitimate product if the sample was printed on the final stock; it is a costly experiment if the sample was digital and the run is offset. Print the sample on the same stock, with the same film, and accept that the sample may cost as much as 10% of the run.
Two other savings work at low volume. Use one die for the card and a stock box with a printed sleeve, so the tooling is limited to the card shape. And keep the finishing to one pass: matte lamination without foil or gilding runs on the same line as the print and does not add a separate curing window.
What does not work: splitting 500 decks into three designs to reach the MOQ. Each design needs its own plates and its own die, so the setup triples. Three designs at 500 each is cheaper than three designs at 167 each.
FAQ
Is MOQ per design or per order?
Per design. Two deck designs in one shipment are two setup costs, so 500 + 500 is treated as two MOQs, not one order of 1,000.
Do samples cost anything?
Standard sample kits are complimentary; you cover the courier. A custom prototype printed on your final stock is quoted separately and is usually credited against the production order.
How long does shipping add?
Express is 3–7 days door to door, air freight 5–10 days plus customs, and sea freight 25–40 days depending on the port. Add 2–4 days for export documents and booking.